On the complexity of open shop scheduling with time lags
Abstract
The minimization of makespan in open shop with time lags has been shown NP-hard in the strong sense even for the case of two machines and unit-time operations. The minimization of total completion time however has remained open for that case though it has been shown NP-hard in the strong sense for weighted total completion time or for jobs with release dates. This note shows that the minimization of total completion time for two machines and unit-time operations is NP-hard in the strong sense which answers the long standing open question.
Explore related subjects
Keep this discovery
Wieslaw Kubiak. 2021-07-16. On the complexity of open shop scheduling with time lags. https://arxiv.org/abs/2107.08102